Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 24O00138

DPWH infrastructure contract
Contract ID:
24O00138
Fingerprint:
4bf5c4b1857a15…a7ce595710 Verified
Status:
On-Going
Physical progress:
60.8%
Timeline:
Start Sep 27, 2024 (2 yrs 1 mo ago)
Description:
CONSTRUCTION OF STAFF OFFICERS QUARTERS BUILDING, HPA, FORT ANDRES BONIFACIO, TAGUIG CITY, PHASE VII
Category:
GAA 2024 CP
Implementing office:
DPWH National Capital Region · National Capital Region
Contractor:
KAEL CONSTRUCTION AND SUPPLY · DPWH contractor code 49152
Location:
Not stated in the source
Contract amount:
₱96,453,661.55 (₱96.5M)
Funding source:
Regular Infra - GAA 2024 CP
Budget year:
2024

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
fda0becd3c64…Sep 13, 2024DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - NCR₱94,342,658.38

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.