Project 24OB0056
DPWH infrastructure contract
Contract ID:
24OB0056
Fingerprint:
63d1300c683f25…ac2348fb51 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Apr 8, 2024 (2 yrs 7 mo ago) · Target/actual end Jan 17, 2025
Description:
REHABILITATION OF BARANGAY TUMANA DRAINAGE SYSTEM, MARIKINA CITY
Category:
Flood Control and Drainage
Implementing office:
DPWH Metro Manila 1st DEO · National Capital Region
Contractor:
MRB11 CONSTRUCTION CORPORATION (FORMERLY:MRB CONS · DPWH contractor code 17701
Contract amount:
₱28,797,915.84 (₱28.8M)
Funding source:
Regular Infra - GAA 2024 OO-2
Budget year:
2024
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25OB0459 | May 22, 2025 | RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES - MARIKINA BR. (B01866LZ) ALONG A BONIFACIO AVE | On-Going | ₱144.9M |
| 25OB0262 | May 20, 2025 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, NANGKA RIVER,MARIKINA CITY | Completed | ₱47.8M |
| 25OB0263 | May 20, 2025 | REHABILITATION OF FLOOD CONTROL STRUCTURE ALONG NANGKA RIVER, MARIKINA CITY | Completed | ₱38.1M |
| 25OB0285 | May 20, 2025 | INSTALLATION OF ROAD SAFETY DEVICES ALONG ORDONEZ STREET, SECOND DISTRICT, MARIKINA CITY | On-Going | ₱38.0M |
| 25OB0287 | May 20, 2025 | INSTALLATION OF ROAD SAFETY DEVICES ALONG F. MANALO STREET INCLUDING LATERALS, BARANGAY NANGKA, MARIKINA CITY | Completed | ₱9.5M |
| 25OB0289 | May 20, 2025 | INSTALLATION OF M. SEVILLA ROAD SAFETY DEVICES INCLUDING LATERALS, BARANGAY PARANG, MARIKINA CITY | Completed | ₱9.3M |
| 25OB0290 | May 20, 2025 | INSTALLATION OF SHOE AVENUE, AMANG RODRIGUEZ, ROAD SAFETY DEVICES, BARANGAY CONCEPCION UNO, MARIKINA CITY | Completed | ₱9.5M |
| 25OB0294 | May 20, 2025 | INSTALLATION OF ORO VISTA SUBDIVISION ROAD SAFETY DEVICES, BARANGAY CONCEPCION UNO, MARIKINA CITY | On-Going | ₱9.5M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.