Project 24OB0159
DPWH infrastructure contract
Contract ID:
24OB0159
Fingerprint:
186fad34402519…35ecd33ad9 Verified
Status:
On-Going
Physical progress:
100%
Timeline:
Start Apr 18, 2024 (2 yrs 6 mo ago)
Description:
CONSTRUCTION OF DRAINAGE OUTFALL INCLUDING LATERALS AT B. MORCILLA ST. AND VICINITY, PATEROS, METRO MANILA
Category:
Flood Control and Drainage
Implementing office:
DPWH Metro Manila 1st DEO · National Capital Region
Contractor:
FRANZCOR TRADING & CONSTRUCTION · DPWH contractor code 18082
Contract amount:
₱12,357,410.30 (₱12.4M)
Funding source:
Regular Infra - GAA 2024 OO-2
Budget year:
2024
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 0831cf0c56a8… | Apr 8, 2024 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - METRO MANILA 1ST E | ₱12,357,410.30 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25OB0363 | Jun 27, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, PATEROS TECHNOLOGICAL COLLEGE, P. HERRERA ST. BRGY. SAN PEDRO, PATEROS (PHASE 1) | On-Going | ₱58.2M |
| 25OB0256 | Mar 20, 2025 | CONSTRUCTION OF RETAINING WALL AND REHABILITATION OF STA. ANA RIVER, PATEROS, METRO MANILA (PACKAGE VIII) | On-Going | ₱48.2M |
| 25OB0117 | Mar 19, 2025 | RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES - STO. ROSARIO BR. (B01879LZ) ALONG PPTA RD | On-Going | ₱9.4M |
| 25OB0272 | Mar 19, 2025 | BANK IMPROVEMENT OF SLOPE PROTECTION ALONG MARIKINA RIVER (PACKAGE 21), PASIG CITY | On-Going | ₱70.2M |
| 25OB0336 | Mar 19, 2025 | REHABILITATION OF MULTI-PURPOSE BUILDING, BARANGAY SUMILANG, PASIG CITY | Completed | ₱14.5M |
| 25OB0337 | Mar 19, 2025 | CONSTRUCTION OF BARANGAY TABACALERA BARANGAY HALL, PATEROS, METRO MANILA | Completed | ₱6.8M |
| 25OB0338 | Mar 19, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, ALVIAR COMPOUND, STA. ANA, PATEROS, METRO MANILA | Terminated | ₱0 |
| 25OB0339 | Mar 19, 2025 | REHABILITATION OF PATEROS ELEMENTARY SCHOOL GYMNASIUM, BARANGAY SAN PEDRO, PATEROS, METRO MANILA | Completed | ₱17.5M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.