Project 24OB0197
DPWH infrastructure contract
Contract ID:
24OB0197
Fingerprint:
fa00dc8df95a40…39825bdb7e Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 13, 2024 (2 yrs 9 mo ago) · Target/actual end Sep 11, 2024
Description:
CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG LABASAN RIVER (WEST BANK) PACKAGE 3, TAGUIG CITY
Category:
Flood Control and Drainage
Implementing office:
DPWH Metro Manila 1st DEO · National Capital Region
Contractor:
TOUGHBUILT CONSTRUCTION & TRADING INC · DPWH contractor code 35947
As listed: TOUGHBUILT CONSTRUCTION & TRADING, INC.
Contract amount:
₱94,569,857.57 (₱94.6M)
Funding source:
Regular Infra - GAA 2024 OO-2
Budget year:
2024
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| b44caad2bfe3… | Jan 30, 2024 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - METRO MANILA 1ST E | ₱94,569,857.57 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25OB0443 | Jul 13, 2026 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. NEW LOWER BICUTAN, TAGUIG CITY (PHASE 1) | On-Going | ₱46.9M |
| 25OB0367 | Apr 15, 2026 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING AND SITE DEVELOPMENT AT LAKESHORE AT BARANGAY LOWER BICUTAN, TAGUIG CITY | On-Going | ₱47.0M |
| 25OB0409 | Aug 14, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, NRCPO, CAMP BAGONG DIWA, TAGUIG CITY | On-Going | ₱29.1M |
| 25OB0437 | Aug 14, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, SPD COMPOUND, LAWTON AVE., BARANGAY WESTERN BICUTAN, TAGUIG CITY (PHASE 1) | On-Going | ₱48.5M |
| 25OC0178 | Jul 8, 2025 | REHABILITATION/IMPROVEMENT OF SOUTH SUPER H-WAY WEST SERVICE RD (S03387LZ)(INTERMITTENT) PARAÑAQUE CITY, METRO MANILA | Completed | ₱12.8M |
| 25OB0371 | Jun 27, 2025 | CONSTRUCTION OF MULTI-PURPOSE FACILITIES AT LAKESHORE, BARANGAY LOWER BICUTAN, TAGUIG CITY (PHASE 1) | On-Going | ₱48.5M |
| 25OB0372 | Jun 27, 2025 | CONSTRUCTION OF MULTI-PURPOSE FACILITIES AT LAKESHORE, BARANGAY LOWER BICUTAN, TAGUIG CITY (PHASE 2) | On-Going | ₱48.5M |
| 25OB0373 | Jun 27, 2025 | CONSTRUCTION OF MULTI-PURPOSE FACILITIES AT LAKESHORE, BARANGAY LOWER BICUTAN, TAGUIG CITY (PHASE 5) | On-Going | ₱72.7M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.