Project 24OD0033
DPWH infrastructure contract
Contract ID:
24OD0033
Fingerprint:
ebe45e9484e639…a2ba15ae48 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 14, 2024 (2 yrs 9 mo ago) · Target/actual end Jul 2, 2024
Description:
CONSTRUCTION OF FLOOD CONTROL WALL ALONG SAMPAGUITA CREEK, BARANGAY 171, CALOOCAN CITY
Category:
Flood Control and Drainage
Implementing office:
DPWH Metro Manila 3rd DEO · National Capital Region
Contractor:
FRAMECON BUILDERS · DPWH contractor code 22482
Contract amount:
₱47,818,676.13 (₱47.8M)
Funding source:
Regular Infra - GAA 2024 OO-2
Budget year:
2024
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 52536e26bc7f… | Jan 31, 2024 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS (METRO MANILA 3RD ED | ₱47,818,676.13 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25OD0370 | Jul 28, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, NORTH OLYMPUS, BARANGAY 172, CALOOCAN CITY | On-Going | ₱9.2M |
| 25OD0371 | Jul 28, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY 156, CALOOCAN CITY | On-Going | ₱10.5M |
| 25OD0373 | Jul 28, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT), CELINA HOMES, BARANGAY 168, CALOOCAN CITY | On-Going | ₱4.8M |
| 25OD0374 | Jul 28, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), PHASE 2, BARANGAY 171, CALOOCAN CITY | Completed | ₱4.8M |
| 25OD0375 | Jul 28, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (SPORTS COMPLEX), BARANGAY 176, CALOOCAN CITY (PHASE 3) | On-Going | ₱23.9M |
| 25OD0376 | Jul 28, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. 180, CALOOCAN CITY | On-Going | ₱28.6M |
| 25OD0368 | Jul 21, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY 153, CALOOCAN CITY | On-Going | ₱28.7M |
| 25OD0360 | Jul 9, 2025 | CONSTRUCTION (COMPLETION) PUP NORTH CALOOCAN CITY CAMPUS ACADEMIC BUILDING INCLUDING GROUND IMPROVEMENT (PHASE 6), BRGY. 168, CALOOCAN CITY | On-Going | ₱139.3M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.