Project 24OD0079
DPWH infrastructure contract
Contract ID:
24OD0079
Fingerprint:
a89e93fbed468b…f879877997 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 27, 2024 (2 yrs 8 mo ago) · Target/actual end Oct 1, 2024
Description:
CONSTRUCTION OF REINFORCED CONCRETE BOX CULVERT ALONG C-3 ROAD (CALOOCAN/NAVOTAS BOUNDARY - DAGAT-DAGATAN AVENUE), CALOOCAN CITY
Category:
GAA 2024 OO-2
Implementing office:
DPWH Metro Manila 3rd DEO · National Capital Region
Contractor:
NOVA VENTUS CONSTRUCTION INC. (53730) / TOUGHBUILT CONSTRUCTION & TRADING, INC. · DPWH contractor code 35947
Contract amount:
₱38,296,975.74 (₱38.3M)
Funding source:
Regular Infra - GAA 2024 OO-2
Budget year:
2024
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25OD0370 | Jul 28, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, NORTH OLYMPUS, BARANGAY 172, CALOOCAN CITY | On-Going | ₱9.2M |
| 25OD0371 | Jul 28, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY 156, CALOOCAN CITY | On-Going | ₱10.5M |
| 25OD0373 | Jul 28, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT), CELINA HOMES, BARANGAY 168, CALOOCAN CITY | On-Going | ₱4.8M |
| 25OD0374 | Jul 28, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), PHASE 2, BARANGAY 171, CALOOCAN CITY | Completed | ₱4.8M |
| 25OD0375 | Jul 28, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (SPORTS COMPLEX), BARANGAY 176, CALOOCAN CITY (PHASE 3) | On-Going | ₱23.9M |
| 25OD0376 | Jul 28, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. 180, CALOOCAN CITY | On-Going | ₱28.6M |
| 25OD0368 | Jul 21, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY 153, CALOOCAN CITY | On-Going | ₱28.7M |
| 25OD0360 | Jul 9, 2025 | CONSTRUCTION (COMPLETION) PUP NORTH CALOOCAN CITY CAMPUS ACADEMIC BUILDING INCLUDING GROUND IMPROVEMENT (PHASE 6), BRGY. 168, CALOOCAN CITY | On-Going | ₱139.3M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.