Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 24OD0107

DPWH infrastructure contract
Contract ID:
24OD0107
Fingerprint:
080c5885a040ba…2d83e8fcf1 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 27, 2024 (2 yrs 8 mo ago) · Target/actual end Sep 16, 2024
Description:
IMPROVEMENT OF ROAD AND DRAINAGE SYSTEM ALONG CAIMITO ROAD, BRGY. 79, CONNECTING TO SAMSON ROAD & MACARTHUR HIGHWAY (PHASE 2), CALOOCAN CITY
Category:
Roads
Implementing office:
DPWH Metro Manila 3rd DEO · National Capital Region
Contractor:
KING EIGHT BUILDERS AND SUPPLY · DPWH contractor code 37325
Contract amount:
₱24,055,320.39 (₱24.1M)
Funding source:
Regular Infra - GAA 2024 SSP
Budget year:
2024

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
cb7cc89f0162…Feb 23, 2024DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS (METRO MANILA 3RD ED₱24,055,320.39

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25OD0370Jul 28, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, NORTH OLYMPUS, BARANGAY 172, CALOOCAN CITYOn-Going₱9.2M
25OD0371Jul 28, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY 156, CALOOCAN CITYOn-Going₱10.5M
25OD0373Jul 28, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT), CELINA HOMES, BARANGAY 168, CALOOCAN CITYOn-Going₱4.8M
25OD0374Jul 28, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), PHASE 2, BARANGAY 171, CALOOCAN CITYCompleted₱4.8M
25OD0375Jul 28, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (SPORTS COMPLEX), BARANGAY 176, CALOOCAN CITY (PHASE 3)On-Going₱23.9M
25OD0376Jul 28, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. 180, CALOOCAN CITYOn-Going₱28.6M
25OD0368Jul 21, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY 153, CALOOCAN CITYOn-Going₱28.7M
25OD0360Jul 9, 2025CONSTRUCTION (COMPLETION) PUP NORTH CALOOCAN CITY CAMPUS ACADEMIC BUILDING INCLUDING GROUND IMPROVEMENT (PHASE 6), BRGY. 168, CALOOCAN CITYOn-Going₱139.3M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.