FY2026 GAA: ₱6.79T
PisoScan

Project 24OG0058

DPWH infrastructure contract
Contract ID:
24OG0058
Fingerprint:
015c88fdcd6307…01af030ec0 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 15, 2024 (2 yrs 9 mo ago) · Target/actual end Sep 16, 2024
Description:
RETROFITTING / STRENGTHENING OF PERMANENT BRIDGES - LIBIS BR. (SB) (B02676LZ) ALONG E RODRIGUEZ JR AVE, QUEZON CITY
Category:
Bridges
Implementing office:
DPWH Quezon City 2nd DEO · National Capital Region
Contractor:
ALPHATEC CHEMICAL CORPORATION · DPWH contractor code 39938
Contract amount:
₱72,372,077.78 (₱72.4M)
Funding source:
Regular Infra - GAA 2024 OO-1
Budget year:
2024

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26OB0090Jun 22, 2026RETROFITTING/STRENGTHENING OF PERMANENT BRIDGE - PASIG BLVD C5 FLYOVER (B01876LZ) ALONG C-5 ROADOn-Going₱74.3M
26OB0088May 21, 2026RETROFITTING/STRENGTHENING OF PERMANENT BRIDGE - C5/ORTIGAS FLYOVER (B03319LZ) ALONG C5- ORTIGAS FLYOVER, PHASE IIOn-Going₱97.8M
26OB0089May 21, 2026RETROFITTING/STRENGTHENING OF PERMANENT BRIDGE - ORTIGAS BR. (B01868LZ) ALONG MANILA EAST RD (ROSARIO-CAINTA RD)On-Going₱89.9M
26OB0091May 12, 2026RETROFITTING/STRENGTHENING OF PERMANENT BRIDGE - C5/ORTIGAS FLYOVER (B03318LZ) ALONG C5- ORTIGAS FLYOVER, PHASE IIOn-Going₱25.4M
26OB0092May 12, 2026RETROFITTING/STRENGTHENING OF PERMANENT BRIDGE - DAAN PASIG BR. (B01874LZ) ALONG AMANG RODRIGUEZ RDOn-Going₱23.8M
25OB0461Jun 20, 2025CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM IN PUBLIC FACILITIES IN METRO MANILA 1ST DISTRICT ENGINEERING OFFICECompleted₱2.6M
25OG0038May 23, 2025CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG MARIKINA RIVER, PHASE 4, BARANGAY BAGUMBAYAN, QUEZON CITYOn-Going₱48.0M
25OG0039May 23, 2025CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG MARIKINA RIVER, PHASE 5, BARANGAY BAGUMBAYAN, QUEZON CITYOn-Going₱48.0M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.