FY2026 GAA: ₱6.79T
PisoScan

Project 25AJ0145

DPWH infrastructure contract
Contract ID:
25AJ0145
Fingerprint:
ddf02b6b4080d8…e7a820a098 Verified
Status:
On-Going
Physical progress:
2.4%
Timeline:
Start May 30, 2025 (1 yr 5 mo ago)
Description:
CONCRETING OF BRGY. MATAGDEM FMR, BRGY. MATAGDEM, SAN CARLOS CITY, PANGASINAN
Category:
GAA 2025 DA FMR
Implementing office:
Contractor:
JEUSMACK BUILDERS & CONSTRUCTION SUPPLY · DPWH contractor code 42334
Contract amount:
₱14,426,384.29 (₱14.4M)
Funding source:
Outside Infra - GAA 2025 DA FMR
Budget year:
2025

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25AJ0101Aug 6, 2025CONSTRUCTION SLOPE PROTECTION, BRGY. PAYAR, SAN CARLOS CITY, PANGASINANOn-Going₱4.8M
25AJ0120Aug 6, 2025ACCESS ROAD LEADING TO MINOR BASILICA OF SAINT DOMINIC DE GUZMAN, SAN CARLOS CITY, PANGASINANOn-Going₱47.2M
25A00545Jul 4, 2025BASIC INFRASTRUCTURE PROGRAM (BIP), CONSTRUCTION OF MULTI - PURPOSE BUILDING, BRGY. TURAC, CITY OF SAN CARLOS, PANGASINANCompleted₱4.8M
25AJ0100Jun 5, 2025CONSTRUCTION OF FLOOD CONTROL (WATER IMPOUNDING), BRGY. RIZAL, SAN CARLOS CITY, PANGASINANOn-Going₱4.8M
25AJ0102Jun 5, 2025CONSTRUCTION OF DRAINAGE CANAL, BRGY. MATAGDEM, SAN CARLOS CITY, PANGASINANOn-Going₱4.8M
25AJ0107Jun 5, 2025CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG SAN JUAN RIVER, BARANGAY MESTIZO NORTE, SAN CARLOS CITY, PANGASINANOn-Going₱19.1M
25AJ0124Jun 5, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PANAMINDITAAN CREEK, BARANGAY TALANG, SAN CARLOS CITY, PANGASINANOn-Going₱47.2M
25AJ0125Jun 5, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SAN JUAN RIVER, BOLOSAN SECTION, SAN CARLOS CITY, PANGASINANOn-Going₱47.2M