Project 25CH0020
DPWH infrastructure contract
Contract ID:
25CH0020
Fingerprint:
fa8204c53c31d3…4258a53249 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 24, 2025 (1 yr 8 mo ago) · Target/actual end Jun 23, 2025
Description:
CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG BARANGAY SAN ANTONIO (PHASE II), FLORIDABLANCA, PAMPANGA
Category:
GAA 2025 SSP
Implementing office:
DPWH Pampanga 2nd DEO · Region III
Contractor:
ARROW CONSTRUCTION · DPWH contractor code 32834
Contract amount:
₱29,395,044.73 (₱29.4M)
Funding source:
Regular Infra - GAA 2025 SSP
Budget year:
2025
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| bdf478c948eb… | Jan 31, 2025 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - PAMPANGA 2ND DEO | ₱28,723,120.98 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CH0063 | Jul 9, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM RAINWATER COLLECTOR SYSTEM, 2ND DISTRICT, PAMPANGA | Completed | ₱2.6M |
| 25CH0038 | Apr 10, 2025 | CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG PORAC RIVER, ASCOMO SECTION, GUAGUA, PAMPANGA | Completed | ₱24.5M |
| 25CH0052 | Apr 10, 2025 | FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG PORAC RIVER, VALDEZ SECTION FLORIDABLANCA, PAMPANGA | Completed | ₱29.4M |
| 24CH0160 | Apr 7, 2025 | REPAIR AND MAINTENANCE OF DAMAGED ROAD SLOPE PROTECTION ALONG CAULAMAN RIVER, DAMPE, FLORIDABLANCA, PAMPANGA | Completed | ₱28.9M |
| 25CH0041 | Apr 7, 2025 | CONSTRUCTION OF ROAD, BARANGAY CALANTAS, FLORIDABLANCA, PAMPANGA | Completed | ₱4.9M |
| 25CH0045 | Apr 7, 2025 | CONSTRUCTIO OF ROAD WITH LINED CANAL, BARANGAY LIGAYA, PULUNGMASLE, GUAGUA, PAMPANGA | Completed | ₱4.9M |
| 25CH0048 | Apr 7, 2025 | CONSTRUCTION OF ROAD, PHASE 2, PUROK 6, BARANGAY PAGUIRUAN, FLORIDABLANCA, PAMPANGA | Completed | ₱4.9M |
| 25CH0049 | Apr 7, 2025 | CONSTRUCTION OF ROAD, BARANGAY DAMPE, FLORIDABLANCA, PAMPANGA, PHASE 2 FLORIDABLANCA, PAMPANGA | Completed | ₱4.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.