Project 25EB0019
DPWH infrastructure contract
Contract ID:
25EB0019
Fingerprint:
9c88e3bf844cb6…cbbbddc91f Verified
Status:
On-Going
Physical progress:
77.5%
Timeline:
Start Mar 24, 2025 (1 yr 7 mo ago)
Description:
CONSTRUCTION OF MISSING LINKS/NEW ROADS-BULALACAO- SAN JOSE- JCT. MAPAYA ROAD, OCCIDENTAL MINDORO
Category:
GAA 2025 OO-1
Implementing office:
DPWH Mindoro Occidental DEO · MIMAROPA Region
Contractor:
BLACER CONSTRUCTION CORP. · DPWH contractor code 32252
Contract amount:
₱57,014,697.74 (₱57.0M)
Funding source:
Regular Infra - GAA 2025 OO-1
Budget year:
2025
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 0737c811a7bd… | Mar 13, 2025 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - MINDORO OCCIDENTAL | ₱57,016,636.14 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26EI0060 | Jul 21, 2026 | ROAD WIDENING - SECONDARY ROADS - CALAPAN SOUTH RD - K0169+820 - K0170+893, K0173+205 - K0173+366, BULALACAO, ORIENTAL MINDORO | On-Going | ₱43.1M |
| 26EI0061 | Jul 21, 2026 | ROAD WIDENING - SECONDARY ROADS - CALAPAN SOUTH RD - K0174 + 125 - K0174 + 504, K0175 + 141 - K0175 + 835, K0176 + 535 - K0177 + 176, K0178 + 348 - K0178 + 564, K0180 + 807 - K0181 + 000, BULALACAO, ORIENTAL MINDORO | On-Going | ₱79.7M |
| 26EI0123 | Jul 21, 2026 | REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROAD - SECONDARY ROADS - CALAPAN SOUTH RD - K0166 + 755 - K0166 + 1016, K0168 + 151 - K0168 + 345, K0169 + 700 - K0169 + 820, MANSALAY - BULALACAO, ORIENTAL MINDORO | On-Going | ₱11.7M |
| 26EI0112 | Jul 7, 2026 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY SAN ISIDRO, BULALACAO, ORIENTAL MINDORO, (121.264167U, 12.307778U) | On-Going | ₱2.9M |
| 26EI0124 | Jun 30, 2026 | REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROAD - SECONDARY ROADS - CALAPAN SOUTH RD - K0174 +504 - K0174 + 786, BULALACAO, ORIENTAL MINDORO | On-Going | ₱6.7M |
| 25EI0150 | Jun 16, 2025 | CONSTRUCTION OF BRIDGE, BRGY. CAMBUNANG, BULALACAO, ORIENTAL MINDORO | Completed | ₱18.4M |
| 25EI0018 | Mar 25, 2025 | CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF CAWACAT RIVER CONTROL STRUCTURE (UPSTREAM), BARANGAY CAMPAASAN, BULALACAO, ORIENTAL MINDORO | Completed | ₱29.2M |
| 25EI0063 | Mar 25, 2025 | ROAD WIDENING-SECONDARY ROADS - CALAPAN SOUTH RD - K0175+835 - K0176+215, BULALACAO, ORIENTAL MINDORO | Completed | ₱14.2M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.