Project 25FD0019
DPWH infrastructure contract
Contract ID:
25FD0019
Fingerprint:
d8b0075b58a264…8aa3a2f2bb Verified
Status:
On-Going
Physical progress:
82.8%
Timeline:
Start Mar 21, 2025 (1 yr 7 mo ago)
Description:
CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE, PUROK 7, BARANGAY POBLACION, LUPI, CAMARINES SUR
Category:
GAA 2025 SSP
Implementing office:
DPWH Camarines Sur 1st DEO · Region V
Contractor:
BICOL GOLDROCK CONSTRUCTION CORPORATION · DPWH contractor code 32376
Contract amount:
₱96,492,423.61 (₱96.5M)
Funding source:
Regular Infra - GAA 2025 SSP
Budget year:
2025
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 3658fe1379d6… | Mar 11, 2025 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CAMARINES SUR 1ST | ₱94,605,987.00 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25F00511 | Oct 7, 2025 | REPAIR/REHABILITATION OF MAUCA BRIDGE DECK, LUPI, CAMARINES SUR (1ST LEGISLATIVE DISTRICT) | On-Going | ₱17.2M |
| 25FD0103 | Aug 8, 2025 | CONSTRUCTION OF CONCRETE ROAD, ZONE 1 LA PURISIMA, LUPI, CAMARINES SUR | On-Going | ₱13.1M |
| 25F00155 | Jul 9, 2025 | ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-BRIDGE PROGRAM-WIDENING OF PERMANENT BRIDGES-RAGAY BR. (B00437LZ) ALONG ROLANDO R. ANDAYA HIGHWAY (PHASE II), RAGAY, CAMARINES SUR (1ST LEGISLATIVE DISTRICT) | On-Going | ₱14.8M |
| 25FD0069 | Jun 30, 2025 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG COLACLING RIVER, BRGY. BULAWAN JR., LUPI, CAMARINES SUR | On-Going | ₱96.5M |
| 25FD0083 | Jun 27, 2025 | CONSTRUCTION OF ROAD, BARANGAY TIBLE, LUPI, CAMARINES SUR | On-Going | ₱139.4M |
| 25F00383 | Jun 24, 2025 | REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - PRIMARY ROAD - ROLANDO R. ANDAYA HIGHWAY - BRGY. CABUTAGAN, LUPI, CAMARINES SUR - K0333+300-K0333+390, LUPI, CAMARINES SUR (1ST LEGISLATIVE DISTRICT) | On-Going | ₱35.7M |
| 25FD0066 | Jun 16, 2025 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG COLACLING RIVER, BRGY. COLACLING, LUPI, CAMARINES SUR | On-Going | ₱95.5M |
| 25F00194 | May 30, 2025 | ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING-PRIMARY ROADS-MAHARLIKA HIGHWAY-K0373+334-K0374+160, LUPI, CAMARINES SUR (1ST LEGISLATIVE DISTRICT) | On-Going | ₱80.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.