FY2026 GAA: ₱6.79T
PisoScan

Project 25GA0005

DPWH infrastructure contract
Contract ID:
25GA0005
Fingerprint:
425d2ef7af5e87…2378bd7399 Verified
Status:
On-Going
Physical progress:
87.1%
Timeline:
Start Mar 3, 2025 (1 yr 8 mo ago)
Description:
AKLAN EAST RD - K0277+600 - K0277+690
Category:
GAA 2025 OO-1
Implementing office:
DPWH Aklan DEO · Region VI
Contractor:
SOLID MERCHANDISING · DPWH contractor code 31609
Contract amount:
₱14,655,326.73 (₱14.7M)
Funding source:
Regular Infra - GAA 2025 OO-1
Budget year:
2025

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
a814c2f4cf15…Feb 21, 2025DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - AKLAN DEO₱14,655,326.73

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25GA0157Sep 18, 2025CONSTRUCTION OF SCHOOL BUILDING, KALIBO PILOT ELEMENTARY SCHOOL, BARANGAY POBLACION, KALIBO, AKLANOn-Going₱14.9M
24GA0253Aug 20, 2025REHABILITATION OF CONCRETING OF ALIPUTOS FMR, BRGY. ALIPUTOS, NUMANCIA, AKLANOn-Going₱8.3M
25GA0023Jun 4, 2025CONSTRUCTION OF REVETMENT WALL ALONG AKLAN RIVER, BRGY. BACHAO SUR, KALIBO, AKLANOn-Going₱60.8M
25GA0122May 26, 2025CONSTRUCTION OF KALIBO GYMNASIUM, BARANGAY BAKHAW NORTE, KALIBO, AKLANOn-Going₱98.5M
25GA0121May 23, 2025CONSTRUCTION OF REVETMENT WALL IN BRGY. BAKHAW NORTE, KALIBO, AKLANOn-Going₱9.6M
25GA0040Apr 3, 2025CONSTRUCTION OF MABULAY ROAD, BARANGAY LINABUAN NORTE, KALIBO, AKLANCompleted₱4.9M
25GA0001Mar 21, 2025AKLAN EAST RD - K0281+000 - K0283+085On-Going₱93.6M
24GA0251Mar 19, 2025CONSTRUCTION OF REVETMENT WALL (FLOOD CONTROL), ALONG AKLAN RIVER, KALIBO, AKLANOn-Going₱24.1M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.