Project 25GL0137

DPWH infrastructure contract
Contract ID:
25GL0137
Fingerprint:
9fb77ea87abebf…30f5a27df0 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jun 3, 2025 (1 yr 5 mo ago) · Target/actual end Jan 17, 2026
Description:
ROAD WIDENING - BACOLOD SOUTH RD - K0051 + 763 - K0052 + 047, K0062 + 519 - K0062 + 577
Category:
GAA 2025 OO-1
Implementing office:
DPWH Negros Occidental 2nd DEO · Negros Island Region
Contractor:
H.L.J. CONSTRUCTION & ENTERPRISES · DPWH contractor code 18080
As listed: H.L.J CONSTRUCTION & ENTERPRISES
Contract amount:
₱22,202,878.45 (₱22.2M)
Funding source:
Regular Infra - GAA 2025 OO-1
Budget year:
2025

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26RB0023Jun 4, 2026PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY -BACOLOD SOUTH RD - K0057 + 183 - K0058 + 737On-Going₱61.5M
25RB0005Jun 25, 2025CONSTRUCTION OF SCHOOL BUILDING, ANAHAW ELEMENTARY SCHOOL, BRGY.ANAHAW, HINIGARAN CITY NEG. OCCCompleted₱5.0M
25RB0006Jun 25, 2025CONSTRUCTION OF SCHOOL BUILDING, ESTEBAN JALANDONI FARM SCHOOL, BRGY. BAGA-AS, HINIGARAN NEG. OCCCompleted₱4.9M
25GL0017Jun 3, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BRGY. MIRANDA, HINIGARAN, NEGROS OCCIDENTALCompleted₱4.9M
25GL0063Jun 3, 2025ROAD CONCRETING AT BARANGAY QUIWI, HINIGARAN, NEGROS OCCIDENTALCompleted₱4.9M
25GL0075Jun 3, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY GARGATO, HINIGARAN, NEGROS OCCIDENTALCompleted₱4.9M
25GL0097Jun 3, 2025IMPROVEMENT OF INTERSECTION AT BACOLOD SOUTH RD - K0052 + 335Completed₱19.6M
25GL0105Jun 3, 2025PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - HINIGARANISABELA RD - K0063 + 100 - K0065 + 163On-Going₱69.6M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.