Project 25HF0004
DPWH infrastructure contract
Contract ID:
25HF0004
Fingerprint:
4762e85522a0b4…adc9593bc0 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 20, 2025 (1 yr 8 mo ago) · Target/actual end Mar 28, 2025
Description:
ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS TOLEDO-PINAMUNGAHAN-ALOGUINSAN-MANTALONGON RD - K0087 + 672 - K0087 +
Category:
Roads
Implementing office:
DPWH Cebu 3rd DEO · Region VII
Contractor:
SUPREA PHILS. DEVELOPMENT CORP. · DPWH contractor code 41868
Contract amount:
₱1,777,622.10 (₱1.8M)
Funding source:
Regular Infra - GAA 2025 OO-1
Budget year:
2025
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25HF0082 | Aug 19, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDING/ FACILITIES TO SUPPORT SOCIAL SERVICES - COMPLETION OF MULTI-PURPOSE BUILDING (HALL OF JUSTICE), POBLACION, BARILI, CEBU | On-Going | ₱49.5M |
| 25H00040 | Jul 7, 2025 | CSSP, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF ROAD LEADING TO BANGAG LAPUS CAVE (PHASE 2), BARILI, CEBU | On-Going | ₱96.5M |
| 25H00085 | Jun 13, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF FLOOD CONTROL STRUCTURE, SITIO CHICOS, BARANGAY GUNTING, BARILI, CEBU | On-Going | ₱4.9M |
| 25H00087 | Jun 13, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY BALAO, BARILI, CEBU | On-Going | ₱4.9M |
| 25HF0088 | Jun 9, 2025 | CONCRETING OF SITIO KANDAHUNOG, BRGY. BALAO FMR, BARILI, CEBU | On-Going | ₱29.3M |
| 25H00031 | Apr 15, 2025 | OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE, SANTA ANA RIVER, BARANGAY CAMPANGGA, BARILI, CEBU | On-Going | ₱183.3M |
| 25HF0072 | Apr 4, 2025 | ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BARILI-ALOGUINSAN COASTAL ROAD | Completed | ₱51.6M |
| 25HF0073 | Apr 4, 2025 | ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM NETWORK DEVELOPMENT PROGRAM CONSTRUCTION OF BY-PASS AND DIVERSION ROADS BARILI - ALOGUINSAN COASTAL ROAD, PHASE 6, CEBU | On-Going | ₱55.8M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.