Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 25OI0031

DPWH infrastructure contract
Contract ID:
25OI0031
Fingerprint:
9890fdba1dfc6c…b4b7f29dcf Verified
Status:
On-Going
Physical progress:
70.2%
Timeline:
Start Jan 31, 2025 (1 yr 9 mo ago)
Description:
CONSTRUCTION OF ROAD INCLUDING DRAINAGE, TIONGQUIAO, LAS PINAS CITY
Category:
Roads
Implementing office:
DPWH Las Piñas-Muntinlupa DEO · National Capital Region
Contractor:
Contract amount:
₱23,847,107.98 (₱23.8M)
Funding source:
Regular Infra - GAA 2025 SSP
Budget year:
2025

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25OC0132Jul 15, 2025REHABILITATION OF C-5 EXTENSION ROAD IN PARAÑAQUE CITY, PARAÑAQUE CITY, METRO MANILAOn-Going₱27.2M
25OI0116Jun 20, 2025COMPLETION OF MULTI-PURPOSE BUILDING AT BARANGAY ZAPOTE, LAS PINAS CITYOn-Going₱3.9M
25OI0117Jun 20, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY TALON 4, LAS PINAS CITYOn-Going₱11.6M
25OI0058Jun 13, 2025COMPLETION OF MULTI PURPOSE BLDG., CAA, LAS PINAS CITY LONE DISTRICOn-Going₱4.9M
25OI0059Jun 13, 2025REHABILITATION OF ROAD INCLUDING DRAINAGE, ILAYA, LAS PINAS CITY LONE DISTRICTOn-Going₱4.9M
25OI0061Jun 13, 2025CONSTRUCTION OF MULTI-PURPOSE BLDG., TALON 2, LAS PINAS CITY LONE DISTRICT PHASE 2.Completed₱7.8M
25OI0062Jun 13, 2025REHABILITATION OF MULTI-PURPOSE BLDG., TALON 4, LAS PINAS CITY LONE DISTRICTOn-Going₱7.8M
25OI0063Jun 13, 2025REHABILITATION OF ROAD INCLUDING DRAINAGE, PAMPLONA 3, LAS PINAS CITY LONE DISTRICTOn-Going₱17.5M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.