Project 25PA0008
DPWH infrastructure contract
Contract ID:
25PA0008
Fingerprint:
05be663e5cffc7…00838e8416 Verified
Status:
On-Going
Physical progress:
90%
Timeline:
Start Mar 19, 2025 (1 yr 7 mo ago)
Description:
CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), DAOIDAO ELEMENTARY SCHOOL, BARANGAY DAOIDAO, SAN JUAN, ABRA
Category:
Buildings and Facilities
Implementing office:
DPWH Abra DEO · Cordillera Administrative Region
Contractor:
739 BUILDERS · DPWH contractor code 31174
Contract amount:
₱4,700,792.06 (₱4.7M)
Funding source:
Regular Infra - GAA 2025 SSP
Budget year:
2025
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 51be6ace5c42… | Feb 26, 2025 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ABRA ED | ₱4,700,792.06 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25PA0142 | Jun 11, 2025 | CONCRETING OF BRGY. SILET FMR, BRGY. SILET, SAN JUAN, ABRA | On-Going | ₱14.1M |
| 24PA0219 | Jan 15, 2025 | CONSTRUCTION OF CULIONG FLOOD CONTROL STRUCTURE ALONG ABRA RIVER BASIN, BARANGAY CULIONG, SAN JUAN, ABRA | On-Going | ₱138.9M |
| 24PA0123 | May 20, 2024 | CONCRETING OF SUPIIL-GALOOS FMR, BRGY. SUPIIL, SAN JUAN, ABRA, SAN JUAN, ABRA | On-Going | ₱14.3M |
| 24PA0135 | May 20, 2024 | CONSTRUCTION OF MALANAS BRIDGE, SAN JUAN, ABRA | On-Going | ₱74.5M |
| 23PA0130 | May 23, 2023 | OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVER, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ABRA MAJOR RIVER BASIN, PAGA, MALABBAGA, LA PA | On-Going | ₱96.5M |
| 23PA0122 | May 8, 2023 | REHABILITATION OF SILET-CAGANAYAN VIA SITIO KAPARKAN ROAD, SAN JUAN AND TINEG, ABRA | Completed | ₱96.5M |
| 23PA0103 | Apr 14, 2023 | OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVER, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG TINEG RIVER, TAGAYTAY, SAN JUAN, ABRA | Completed | ₱77.2M |
| 22PA0213 | Jul 20, 2022 | SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF MALANAS BRIDGE, BADAS & POBLACION, SAN JUAN, ABRA | Completed | ₱96.5M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.