Project 16MG0148
DPWH infrastructure contract
Contract ID:
16MG0148
Fingerprint:
706fe48e1e5845…51d7789ce7 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jan 2, 2017 (9 yrs 10 mo ago) · Target/actual end Jan 31, 2018
Description:
CONSTRUCTION OF 1UNIT - 1STY 3CL AT TUDOK ES, T'BOLI, SOUTH COTABATO
Category:
Buildings and Facilities
Implementing office:
DPWH South Cotabato 2nd DEO · Region XII
Contractor:
STONELINE CONSTRUCTION · DPWH contractor code 13132
As listed: STONELINE CONSTRUCTION (FORMERLY: ABUBAKAR ENGINEERING EXPONENT)
Contract amount:
₱3,168,619.39 (₱3.2M)
Funding source:
Outside Infra - GAA 2016 DepED BEFF
Budget year:
2016
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| c1eebe3abbde… | Dec 9, 2016 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - SOUTH COTABATO DEO | ₱3,168,619.39 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26MG0049 | Aug 17, 2026 | CONSTRUCTION OF CONCRETE ROAD-JCT. LANG DULAY ROAD LEADING TO BRGY. LAMDALAG-BRGY. KLUBI-BRGY. LAMCADE (SITE OF WORLD'S MOST NUMBER OF T'NALAK WEAVERS), BRGY. KLUBI, LAKE SEBU, STA.0+000-STA.0+205 SOUTH COTABATO | On-Going | ₱4.2M |
| 26MG0040 | Jun 29, 2026 | CONSTRUCTION OF ROAD, BARANGAY AFLEK, T'BOLI, STA.0+000-STA.0+227 SOUTH COTABATO | Completed | ₱4.6M |
| 25MG0120 | Feb 6, 2026 | REPAIR/REHABILITATION OF CLASSROOMS, LUGAN CENTRAL ELEMENTARY SCHOOL, T'BOLI, SOUTH COTABATO | Completed | ₱16.3M |
| 25M00027 | Jul 15, 2025 | REHABILITATION/RECONSTRUCTION OF ROADS SLIPS, SLOPE COLLAPSE, AND LANDSLIDE-GENERAL SANTOS CITY-T'BOLI-SURALLAH RD - (S01483MN)K1682+674-K1682+748.98, K1683+915-K1684+012, K1685+106-K1685+204, K1686+113-K1686+136, K1686+184-K1686+232, GENERAL SANTOS CITY, | On-Going | ₱180.5M |
| 25M00179 | Jul 9, 2025 | REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - GENERAL SANTOS CITY-T'BOLI-SURALLAH RD - K1680 + 997 - K1681 + 030, K1681 + 050 - K1681 + 085, K1681 + 969 - K1682 + 014, K1681 + 986 - K1682 + 020, GENERAL SANTOS CITY | Completed | ₱73.7M |
| 25MG0064 | Apr 11, 2025 | CONSTRUCTION OF ROAD, MACULAN-HALILAN ROAD, LAKE SEBU, SOUTH COTABATO | Completed | ₱9.8M |
| 25MG0065 | Apr 11, 2025 | CONSTRUCTION OF ROAD, SITIO KLEENG, BARANGAY MAAN, T'BOLI, SOUTH COTABATO | On-Going | ₱7.3M |
| 25MG0091 | Apr 11, 2025 | CONSTRUCTION OF CONCRETE ROAD-JCT. LANG DULAY ROAD LEADING TO BRGY LAMDALAG-BRGY. KLUBI-BRGY. LAMCADE (SITE OF WORLD'S MOST NUMBER OF T'NALAK WEAVERS), BRGY. KLUBI, LAKE SEBU, SOUTH COTABATO | Completed | ₱12.4M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.