Project 17CD0127
DPWH infrastructure contract
Contract ID:
17CD0127
Fingerprint:
2c1e970a534f56…5e5f199f3e Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 30, 2017 (9 yrs 7 mo ago) · Target/actual end Jun 27, 2017
Description:
RIPRAPPING / CONSTRUCTION OF RIVERWALL, UBIHAN, MEYCAUAYAN CITY, BULACAN
Category:
Flood Control: Construction - Slope Protection using non - structural measures (e.g. vetiver, coconet, other vegetation), Flood Control: Construction - Slope Protection using Structural Measures (e.g., Revetment, Retaining Structures, Rock Netting, Concrete Crib, Shotcrete, MSE Walls, Gabions, Riprap, Masonry)
Implementing office:
DPWH Bulacan 2nd DEO · Region III
Contractor:
C.L. MORALES CONSTRUCTION AND TRADING · DPWH contractor code 38367
Contract amount:
₱1,925,260.75 (₱1.9M)
Funding source:
Regular Infra - Flood Control: Construction - Slope Protection using non - structural measures (e.g. vetiver, coconet, other vegetation), Flood Control: Construction - Slope Protection using Structural Measures (e.g., Revetment, Retaining Structures, Rock Netting, Concrete Crib, Shotcrete, MSE Walls, Gabions, Riprap, Masonry)
Budget year:
2017
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| d7d6c979fdbd… | Mar 20, 2017 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BULACAN 2ND DEO | ₱1,925,260.75 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25OD0320 | Jul 31, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (3S CENTER BUILDING) AT BARANGAY COLOONG, VALENZUELA CITY | On-Going | ₱99.3M |
| 25CD0231 | Jul 14, 2025 | CONSTRUCTION OF LONGOS PUMPING STATION ALONG MEYCAUAYAN RIVER, MEYCAUAYAN CITY, BULACAN | On-Going | ₱93.6M |
| 25OD0347 | Jun 23, 2025 | CONSTRUCTION OF ROAD AND DRAINAGE, PHASE 2, BARANGAY TAGALAG, VALENZUELA CITY | Completed | ₱11.5M |
| 25CD0195 | May 26, 2025 | REHABILITATION OF VARIOUS PUMPING STATIONS ALONG MAJOR RIVER BASINS, MARILAO & MEYCAUAYAN RIVER, BULACAN | On-Going | ₱47.5M |
| 25OD0096 | May 26, 2025 | CONSTRUCTION OF ROADS AND DRAINAGES ALONG TAGALAG EXTENSION, BARANGAY TAGALAG, VALENZUELA CITY | On-Going | ₱38.5M |
| 25OD0100 | May 26, 2025 | REHABILITATION OF ROADS AD DRAINAGES ALONG N. CALIXTO ST., BARANGAY WAWANG PULO, VALENZUELA CITY | Completed | ₱9.7M |
| 25OD0138 | May 26, 2025 | REHABILITATION OF ROAD AND DRAINAGE ALONG SALAMBAO ST., BARANGAY WAWANG PULO, VALENZUELA CITY | Completed | ₱21.2M |
| 25OD0172 | May 26, 2025 | CONSTRUCTION OF FLOOD CONTROL WALL ALONG POLO RIVER (PHASE 21), VALENZUELA CITY | On-Going | ₱94.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.