Project 17FE0013
DPWH infrastructure contract
Contract ID:
17FE0013
Fingerprint:
6b33da0f1f181e…0370f9bdd4 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Apr 23, 2017 (9 yrs 6 mo ago) · Target/actual end Oct 15, 2018
Description:
NETWORK DEVELOPMENT: IMPROVEMENT/WIDENING OF NATIONAL ROADS TERTIARY ROADS, HANAWAN-CONSOCEP ROAD, OCAMPO, CAMARINES SUR
Category:
Flood Control/Hydraulics/Drainage, Roads: Construction - PCCP
Implementing office:
DPWH Camarines Sur 3rd DEO · Region V
Contractor:
R.K.X. ODIAMAR CONSTRUCTION · DPWH contractor code 16107
Contract amount:
₱27,959,670.19 (₱28.0M)
Funding source:
Regular Infra - Flood Control/Hydraulics/Drainage, Roads: Construction - PCCP
Budget year:
2017
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26FG0016 | Jun 26, 2026 | REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES, BALANGAO BR. (B02379LZ) ALONG PILI-TIGAON-ALBAY BDRY RD.TIGAON, CAMARINES SUR | On-Going | ₱18.6M |
| 25FF0006 | Aug 1, 2025 | 001;NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING-SECONDARY ROADS-PILI TIGAON ALBAY BDRY ROAD-KO457+499-KO459+323,KO459+355.13-KO459+912 OCAMPO CAMARINES SUR | On-Going | ₱94.8M |
| 25FF0028 | Apr 14, 2025 | ORGANIZATIONAL OUTCOME 1:ENSURE SAFE & RELIABLE NATL. RD. SYSTEM-WIDENING OF PERMANENT BRIDGES-HIMAAO BR,(B00409LZ) ALONG PILI TIGAON ALBAY BDRY. ROAD | On-Going | ₱30.1M |
| 25FF0001 | Mar 26, 2025 | 002;CONST./MAINT. OF FLOOD MITIGATION STRUCTURES& DRAINAGE SYSTEM-CONST. OF FLOOD PROTECTION STRUCTURE ALONG HIBAGO RIVER FLOOD MITIGATION STRUCTURE,RIGHT SIDE UPSTREAM OF HIBAGO RIVER BGY. PINIT OCAMPO CAM SUR | Completed | ₱31.4M |
| 24FF0092 | Aug 16, 2024 | CONCRETING OF FARM TO MILL ROAD,BRGY STO NINO OCAMPO CAMARINES SUR | Completed | ₱2.8M |
| 24FF0076 | Jul 16, 2024 | CONCRETING OF ZONE 5, BRGY. PINIT FMR,BRGY PINIT OCAMPO CAMARINES SUR | Completed | ₱16.9M |
| 24FF0079 | Jul 12, 2024 | CONSTRUCTION OF SCHOOL BUILDING, OCAMPO CENTRAL SCHOOL, BRGY. POBLACION CENTRAL, OCAMPO CAMARINES SUR | Completed | ₱4.9M |
| 24FG0079 | Jun 26, 2024 | ROAD WIDENING ALONG PILI-TIGAON-ALBAY BOUNDARY ROAD, K0473+(-831.00) - K0473+718.80, TIGAON, CAMARINES SUR | On-Going | ₱81.5M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.