Project 17Z00004
DPWH infrastructure contract
This contract as an OC4IDS project record, the infrastructure standard used by OpenGovChain. Download: JSON
{
"id": "oc4ids-pisoscan-dpwh-17Z00004",
"title": "REHABILITATION OF DIKE SYSTEM ALONG MADONGAN RIVER (BREACHED AND ERODED DIKE, LEFT AND RIGHT BANK), LAOAG RIVER BASIN FLOOD CONTROL AND SABO PROJECT",
"sector": [
"Flood Control: Construction - Channel Excavation, Flood Control: Construction - Slope Protection using Structural Measures (e.g., Revetment, Retaining Structures, Rock Netting, Concrete Crib, Shotcrete, MSE Walls, Gabions, Riprap, Masonry)"
],
"status": "completed",
"publicAuthority": {
"name": "DPWH Flood Control Management Cluster"
},
"period": {
"startDate": "2017-09-11",
"endDate": "2020-12-23"
},
"budget": {
"amount": {
"amount": 862857754.67,
"currency": "PHP"
}
},
"locations": [
{
"geometry": {
"type": "Point",
"coordinates": [
120.72764,
18.08008
]
}
}
],
"parties": [
{
"name": "TOKWING CONSTRUCTION, CORP.(FOR; TOKWING CONSTRUC",
"roles": [
"supplier"
]
}
],
"contractingProcesses": [
{
"id": "17Z00004",
"summary": {
"title": "REHABILITATION OF DIKE SYSTEM ALONG MADONGAN RIVER (BREACHED AND ERODED DIKE, LEFT AND RIGHT BANK), LAOAG RIVER BASIN FLOOD CONTROL AND SABO PROJECT",
"status": "closed",
"contractValue": {
"amount": 862857754.67,
"currency": "PHP"
}
}
}
],
"pisoscan": {
"dpwhStatus": "Completed",
"physicalProgressPercent": 100,
"fundingSource": "Regular Infra - Flood Control: Construction - Channel Excavation, Flood Control: Construction - Slope Protection using Structural Measures (e.g., Revetment, Retaining Structures, Rock Netting, Concrete Crib, Shotcrete, MSE Walls, Gabions, Riprap, Masonry)",
"sourceDataset": "DPWH contract list via BetterGov.ph",
"sha256": "14c37e04780874784cb49d5d6793f485aec35c797df1bb9fe6895bb50697d543"
}
}