Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 22EH0087

DPWH infrastructure contract
Contract ID:
22EH0087
Fingerprint:
695f549ba12c5f…14e80ba8fe Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 25, 2022 (4 yrs 3 mo ago) · Target/actual end Aug 21, 2023
Description:
CONSTRUCTION OF POBLACION SHORE PROTECTION/CAUSEWAY PHASE II, STA. 0+000 - STA. 0+173, BANTON, ROMBLON
Category:
GAA 2022 CSSP
Implementing office:
DPWH Romblon DEO · MIMAROPA Region
Contractor:
SUNWEST, INC. · DPWH contractor code 15906
As listed: SUNWEST, INC. (FORMERLY: SUNWEST CONSTRUCTION & DEVELOPMENT CORPORATION)
Contract amount:
₱95,293,750.00 (₱95.3M)
Funding source:
Regular Infra - GAA 2022 CSSP
Budget year:
2022

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25EH0118May 26, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BRGY. TOCTOC, BANTON, ROMBLONCompleted₱14.6M
24EH0178Feb 24, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY HAMBI-AN, BANTON, ROMBLONCompleted₱9.9M
23EH0145Jul 14, 2023CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. SIBA, BANTON, ROMBLONCompleted₱11.9M
23EH0141Jun 15, 2023CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. TOGBONGAM, BANTON, ROMBLONCompleted₱11.9M
23EH0115Jun 8, 2023CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. LIBTONG, BANTON, ROMBLONCompleted₱11.9M
23EH0060Mar 29, 2023CONSTRUCTION OF SEAWALL/CAUSEWAY/BAYWALK, PHASE 2, BARANGAY POBLACION, BANTON, ROMBLONCompleted₱96.0M
23EH0071Mar 29, 2023CONSTRUCTION OF STORM SURGE PROTECTION STRUCTURE/CAUSEWAY, POBLACION, BANTON, ROMBLONCompleted₱94.6M
22EH0166Feb 9, 2023CONSTRUCTION OF ELEMENTARY AND SECONDARY CLASSROOM UNDER THE DEPED'S BASIC EDUCATIONAL FACILITIES FUNDS (BEFF) - BATCH 2, 1STY2CL, TUNGONAN NATIONAL HIGH SCHOOL, BANTON, ROMBLONCompleted₱4.5M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.