FY2026 GAA: ₱6.79T
PisoScan

Project 24EH0178

DPWH infrastructure contract
Contract ID:
24EH0178
Fingerprint:
84e14b5d67f4c6…f48f5012d1 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 24, 2025 (1 yr 8 mo ago) · Target/actual end Nov 4, 2025
Description:
CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY HAMBI-AN, BANTON, ROMBLON
Category:
Unprogrammed Appropriations 2024
Implementing office:
DPWH Romblon DEO · MIMAROPA Region
Contractor:
LOTA CONSTRUCTION · DPWH contractor code 54383
Contract amount:
₱9,897,802.66 (₱9.9M)
Funding source:
Outside Infra - Unprogrammed Appropriations 2024
Budget year:
2024

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25EH0118May 26, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BRGY. TOCTOC, BANTON, ROMBLONCompleted₱14.6M
23EH0145Jul 14, 2023CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. SIBA, BANTON, ROMBLONCompleted₱11.9M
23EH0141Jun 15, 2023CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. TOGBONGAM, BANTON, ROMBLONCompleted₱11.9M
23EH0115Jun 8, 2023CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. LIBTONG, BANTON, ROMBLONCompleted₱11.9M
23EH0060Mar 29, 2023CONSTRUCTION OF SEAWALL/CAUSEWAY/BAYWALK, PHASE 2, BARANGAY POBLACION, BANTON, ROMBLONCompleted₱96.0M
23EH0071Mar 29, 2023CONSTRUCTION OF STORM SURGE PROTECTION STRUCTURE/CAUSEWAY, POBLACION, BANTON, ROMBLONCompleted₱94.6M
22EH0166Feb 9, 2023CONSTRUCTION OF ELEMENTARY AND SECONDARY CLASSROOM UNDER THE DEPED'S BASIC EDUCATIONAL FACILITIES FUNDS (BEFF) - BATCH 2, 1STY2CL, TUNGONAN NATIONAL HIGH SCHOOL, BANTON, ROMBLONCompleted₱4.5M
22EH0087Jul 25, 2022CONSTRUCTION OF POBLACION SHORE PROTECTION/CAUSEWAY PHASE II, STA. 0+000 - STA. 0+173, BANTON, ROMBLONCompleted₱95.3M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.