Project 23HB0006
DPWH infrastructure contract
Contract ID:
23HB0006
Fingerprint:
81d4abd9cb4573…38e7c55a5c Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 10, 2023 (3 yrs 9 mo ago) · Target/actual end Nov 11, 2023
Description:
ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM- ASSET PRESERVATION PROGRAM -REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS BALILIHAN-HANOPOL-BATUAN RD - K0040 + (-493.50) - K
Category:
Roads
Implementing office:
DPWH Bohol 3rd DEO · Region VII
Contractor:
Contract amount:
₱43,118,439.44 (₱43.1M)
Funding source:
Regular Infra - GAA 2023 OO-1
Budget year:
2023
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25HA0087 | Jun 2, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, AMBUAN, CATIGBIAN, BOHOL | Completed | ₱4.9M |
| 25HA0088 | Jun 2, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, CAMBAILAN, CATIGBIAN, BOHOL | Completed | ₱4.9M |
| 25HA0089 | Jun 2, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, KANG-IRAS, CATIGBIAN, BOHOL | Completed | ₱4.9M |
| 25HA0090 | Jun 2, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, MAITUM, CATIGBIAN, BOHOL | Completed | ₱4.9M |
| 25HA0091 | Jun 2, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, LIBORON, CATIGBIAN, BOHOL | Completed | ₱4.9M |
| 25HA0106 | Jun 2, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, CAUSWAGAN NORTE, CATIGBIAN, BOHOL | Completed | ₱4.8M |
| 25HA0107 | Jun 2, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, CANDUMAYAO, CATIGBIAN, BOHOL | Completed | ₱4.8M |
| 25HA0108 | Jun 2, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BONGBONG, CATIGBIAN, BOHOL | Completed | ₱4.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.